Return To Project List

Arnold AFB - Replace Unit Substation & Power Panels

Contact Number-Award Date
FA9101-10-C-0037-10/6/2010

Owner-Location
Departemnt of The Army
Arnold Air Force Base, TN

Start Date-Completion Date
10/13/2010-5/10/2011

Contract Amount
$332,707

General Contractor
A. West Enterprise
Project Manager: Chris Joiner
Job Supervisor: Vincent Robinson

Project Description

          The work consisted of providing all the materials, equipment, labor, and tools to remove one unit substation transformer, low voltage switchgear, and primary switch, and install new pad mounted primary switchgear, pad mounted transformer, switchboard and replace electrical panels and other electrical equipment at the Main Cafeteria Facility 452 at Arnold Air Force Base Tennessee. A West Enterprise Project