MCLB LAV & Clearspan

Contact Number-Award Date
140203-07

Owner-Location
NAVFAC

Start Date-Completion Date
5/2015-8/2015

Contract Amount
$254,038.00

General Contractor
Drace Anderson
Project Manager: Lavon Davis

Project Description

       This job consists of installing the electrical scope of work for two clearspans at MCLB Albany.  We will install a total of 3,880 feet of conduit, 11,610' of wire and cable, 18 lights, and 2 panels.  We will provide fire alarm and lightning protection via subs.