Return To Project List

Shaw Arc Flash Corrections

Contact Number-Award Date
140203-07

Owner-Location
Shaw Industries

Start Date-Completion Date
05/2015-07/2015

Contract Amount
$225,186.00

General Contractor
A West Enterprise
Project Manager: Lavon Davis

Project Description

       This job consist of setting a new 800 amp motor control center, a 1600 amp 2 section switchboard, one 225 amp panel, and three 800 amp panels provided by Shaw.  We will install 3,050 feet of aluminum conduit ranging from 3/4" to 4".  We will pull 15,160 feet of cable ranging from #10 to 600 MCM.  We will remove an 800 amp MCC, 8 panels, two runs of buss duct and a unit substation.  Shaw will retain the buss duct and unit substation.  All other salvage rights belong to us.