Clemson University Deferred Maintenance - Package B


Primary Contractor:
A. West Enterprise
705 Canal Street
Albany, GA 31707
Owner: Clemson University
Location: Clemson University Clemson, SC
Contract #:
H12-9898-JM
AWE 140203

A. West Project Manager:
Senior Project Manager - Edward West

Cost:
$1,284,329

Start Date:
May 1, 2014

End Date:
March 1, 2016

  • Project Description:
    The scope of this project consisted of coverting the electrical distribution at Y-Beach area to 15kV. A. West replaced the West campus substation 15kV distribution switch and transformers. The transformers inside Long Hall were replaced with an outdoor pad-mount transformer and the existing main disconnect was replaced with a new 480V switchboard. The 15kV electrical distribution in this area was reworked with new distribution switches and cabling.

Download Printable PDF