Eglin Air Force Base Replace Substation Breakers


Primary Contractor:
A. West Enterprise
705 Canal Street
Albany, GA 31707
Owner: Commander, 96th Civil Engineering Group
Location: Eglin Air Force Base, FL
Contract #:
FTFA 09-1189
AWE 120341

A. West Project Manager:
Lavon Davis

Cost:
$396,587

Start Date:
December 4, 2012

End Date:
January 22, 2013

  • Project Description:
    The scope of this project consisted of nine GE substation breakers with two new Siemens breakers. This was done with the base operating by switching circuits to allow work on the breakers without shutting power off to the base. The work was done in three different substation yards across the base.