FDA Building 9 Switchgear Replacement


Primary Contractor:
CORE Engineering & Construction, Inc.
1020 Railroad Avenue
Winter Park, FL 32789
Owner: National Center for Toxicological Research
Location: Jefferson, AR
Contract #:
HHSF223201400139C
AWE 150201

A. West Project Manager:
Jeremy Meads

Cost:
$1,450,805

Start Date:
September 26, 2014

End Date:
October 30, 2015

  • Project Description:
    The scope of this project consisted of the replacement of a 15kV medium voltage switch, demolishing the existing MV switchgear, and installation of a new switchgear. As well as the demolishment and rewiring of the switchgear building 9 and installation of a 1206KVAR capacitor bank in order to make the system more efficient.

Download Printable PDF