MCLB Install Generator Building 3500


Primary Contractor:
SAIC
1710 SAIC Drive
Mclean, VA 22102
Owner: Marine Corp Logistics Base
Location: Albany, GA
Contract #:
ECM-SPM 500-02-D0121
AWE 130203

A. West Project Manager:
Jeremy Meads

Cost:
$969,408

Start Date:
October 10, 2013

End Date:
December 19, 2014

  • Project Description:
    The scope of this project consisted of intercepting an existing duct bank and installing a new 750kW generator, 15kV paralleling switchgear, 750kVA step up transformer, and associated conduit, conductors, and concrete equipment pads.