NASA Safety & Reliability Upgrades Phase 3


Primary Contractor: ARS Aleut Remediation
Owner: NASA - John F. Kennedy Space Center
Location: Kennedy Space Center, Fl. 32899


Cost:
$3,532,823

Start Date:
October 2018
End Date:
2021


Print this Page

Project Description:
The scope of this project consisted of providing labor, material and equipment to replace Unit Substation SS-1139 and replace underground 15kV Feeders at Kennedy Space Center. Existing SS-1139 was demolished and new a unit substation SS-1139 was installed with pad-mounted transformers and transfer switches. Feeders. Lead cables on Feeders 101, 102, 201, 207, and 214 were removed and replaced with 15kV concentric cable.